Three phases of the Three Gorges Project
( 2003-07-01 17:31) (Chinadaily.com.cn)

Three Construction Phases

First phase, 1993-1997 (five years): Project preparation and first stage of construction, culminating in the damming of the Yangtze River in November 1997. The water of the Yangtze River was diverted through a man-made canal - the diversion channel, and the water level in the Three Gorges area rose by as much as 10 meters as a result.


Second phase, 1998-2003 (six years): The second stage culminates in the first batch of turbines beginning to generate hydropower and the permanent shiplock being put into operation. The reservoir is filled between June 1 and 15, 2003, when the water level in the Three Gorges have risen from the previous 66 meters above sea level to the current 135 meters.

TGP-Second Phase


Third phase
, 2004-2009 (six years): The project is to be completed in 2009, when all 26 generators will be operating. The water level will be raised to 156 meters in September 2006. At the completion of the project in 2009, the water level will reach 175 meters, referred to as the "normal pool level.
TGP Third Phase




   
Close  
  Go to Another Section  
     
 
 
     
  Article Tools  
     
  E-Mail This Article
Print Friendly Format
 
     
   
        .contact us |.about us
  Copyright By chinadaily.com.cn. All rights reserved  
主站蜘蛛池模板: 欧美a在线观看| 色婷婷综合激情视频免费看| 少妇大胆瓣开下部自慰| 亚洲AV日韩AV永久无码色欲| 精品久久久无码中文字幕天天| 国产精品VA在线观看无码不卡| 一个人看的毛片| 日韩AV无码一区二区三区不卡 | 久久久久国产精品免费免费搜索| 欧美极品在线观看| 午夜aaaaaaaaa视频在线| 91香蕉短视频| 国产美女视频网站| 一个人看的www免费高清中文字幕 一个人看的www在线免费视频 | 粉嫩大学生无套内射无码卡视频| 国产啪精品视频网站丝袜| 538精品视频在线观看| 完全免费在线视频| 久久久久久久久久久久久久久久久久| 欧美夫妇交换完整版随便看| 伊人色综合九久久天天蜜桃| 色一情一乱一乱91av| 国产成人精品久久一区二区小说 | 乱中年女人伦av三区| 永久免费AV无码网站性色AV| 午夜私人影院免费体验区| 韩日午夜在线资源一区二区| 国产精品成人久久久久| caoporn地址| 成人免费视频一区二区三区| 久久天天躁夜夜躁狠狠躁2020| 欧美成a人片在线观看久| 人妖系列精品视频在线观看| 美女大量吞精在线观看456 | 久久久久久久综合色一本| 欧美videos另类极品| 亚洲熟妇av一区二区三区宅男| 精品一区二区三区在线观看| 国产一区二区不卡老阿姨| 黑人巨鞭大战欧美肥妇| 国产精品欧美亚洲韩国日本|